Module 2: Project Planning with AI

Create comprehensive WBS, timelines, and resource plans in 30 minutes instead of 4-6 hours

๐Ÿ“š Week 1 ๐ŸŽฏ Beginner

๐ŸŽฏ Learning Objectives

By the end of this module, you will be able to:

The Planning Time Drain

You've just been assigned a new project. Your executive sponsor wants a detailed plan by end of week. Here's what you're facing:

Total: 10.5 hours of intense planning workโ€”and you haven't even started the project yet.

With ChatGPT, you can create the same comprehensive plan in 30 minutes. Here's how.

๐Ÿ“‹ Creating a Work Breakdown Structure with AI

A Work Breakdown Structure (WBS) is the foundation of project planning. It breaks your project into manageable phases, deliverables, and tasks. Here's how to create one with ChatGPT.

The 4-Step WBS Creation Process

1๏ธโƒฃ

Define Project Scope

Clearly describe what the project will deliver and any constraints

2๏ธโƒฃ

Generate Initial WBS

Use AI to create the high-level structure and major phases

3๏ธโƒฃ

Drill Down into Tasks

Break each phase into detailed, actionable tasks

4๏ธโƒฃ

Refine & Validate

Review with your team and adjust based on their expertise

Example: E-Commerce Website Redesign

Let's walk through a real example. You're managing an e-commerce website redesign project.

๐Ÿ’ก Pro Tip: Provide Rich Context

The more context you give ChatGPT, the better your WBS will be. Include:

  • Project goal (what success looks like)
  • Key deliverables (website features, integrations)
  • Team structure (design, dev, QA, stakeholders)
  • Timeline constraints (launch date, milestones)
  • Budget or resource limits (if relevant)

Step 1: The Initial Prompt

I'm managing an e-commerce website redesign project. Help me create a comprehensive Work Breakdown Structure (WBS).

PROJECT DETAILS:
- Goal: Redesign our B2C e-commerce site to increase conversion rate by 30%
- Timeline: 4-month project with November 15 launch deadline
- Team: 2 UX designers, 3 developers, 1 QA engineer, 1 content writer
- Key Features: New homepage, product pages, checkout flow, mobile optimization, payment gateway integration

REQUIREMENTS:
- Break down into major phases (Discovery, Design, Development, Testing, Launch)
- Include all deliverables and tasks
- Consider dependencies between tasks
- Format as a hierarchical structure (Level 1: Phases, Level 2: Deliverables, Level 3: Tasks)
- Include estimated effort (hours or days) for each task

โœ… What Makes This Prompt Effective?

  • Specific project type (e-commerce redesign, not just "website")
  • Clear success criteria (30% conversion increase)
  • Team composition (helps AI understand resource constraints)
  • Structured requirements (phases, dependencies, format)
  • Request for estimates (makes it actionable)

Step 2: Review the Output

ChatGPT will generate a comprehensive WBS. Here's what you'll typically get:

WORK BREAKDOWN STRUCTURE: E-Commerce Website Redesign

1.0 DISCOVERY & PLANNING (2 weeks)
    1.1 Stakeholder Alignment
        1.1.1 Conduct kickoff meeting with sponsors (4 hours)
        1.1.2 Document business objectives and KPIs (8 hours)
        1.1.3 Define success metrics (4 hours)
    
    1.2 User Research
        1.2.1 Analyze current site analytics (16 hours)
        1.2.2 Conduct user interviews (20 hours)
        1.2.3 Create user personas (12 hours)
        1.2.4 Map current user journey (8 hours)
    
    1.3 Competitive Analysis
        1.3.1 Research competitor websites (12 hours)
        1.3.2 Benchmark features and UX patterns (8 hours)
        1.3.3 Document best practices (4 hours)

2.0 DESIGN PHASE (4 weeks)
    2.1 UX Design
        2.1.1 Create information architecture (16 hours)
        2.1.2 Design wireframes for all pages (40 hours)
        2.1.3 Conduct usability testing on wireframes (16 hours)
        2.1.4 Revise based on feedback (12 hours)
    
    2.2 Visual Design
        2.2.1 Develop design system (colors, typography, components) (24 hours)
        2.2.2 Create high-fidelity mockups (48 hours)
        2.2.3 Design mobile-responsive versions (24 hours)
        2.2.4 Stakeholder review and approval (8 hours)

[... continues with Development, Testing, and Launch phases ...]

Step 3: Drill Down Further

Need more detail on a specific phase? Just ask:

Expand section 3.0 Development Phase in more detail. Break down the checkout flow development into specific technical tasks, including:
- Frontend development tasks
- Backend API development
- Payment gateway integration steps
- Database schema changes
Include dependencies and specific technologies (React, Node.js, Stripe)

Step 4: Export to Your PM Tool

Once you're happy with the WBS, get it in a format you can use:

Export this WBS in CSV format with columns: Task ID, Task Name, Phase, Estimated Hours, Dependencies, Assigned Team Member Role

Make it ready to import into Microsoft Project or Jira.

โฑ๏ธ Creating Project Timelines with Dependencies

A WBS tells you what needs to be done. A timeline tells you when and in what order.

Understanding Task Dependencies

๐Ÿ”—

Finish-to-Start (FS)

Task B can't start until Task A finishes. Most common.

Example: Can't start Development until Design is approved

๐Ÿ”€

Start-to-Start (SS)

Task B can start when Task A starts (parallel work).

Example: Content writing starts when Design starts

๐Ÿ

Finish-to-Finish (FF)

Task B must finish when Task A finishes.

Example: Testing finishes when final bug fixes finish

โšก

Start-to-Finish (SF)

Task B can't finish until Task A starts. Rarely used.

Example: Old system runs until new system starts

Creating a Timeline with ChatGPT

Now let's turn your WBS into a realistic project timeline:

Based on the WBS we created, generate a project timeline for the e-commerce redesign project.

CONSTRAINTS:
- Project must complete by November 15 (16 weeks from today)
- Team works 40 hours/week
- Developers can only work 1 feature at a time
- Design must be approved before development starts
- Testing requires completed development

PLEASE PROVIDE:
1. Start and end dates for each major phase
2. Critical path (tasks that directly impact the end date)
3. Task dependencies (which tasks must finish before others start)
4. Identification of any resource conflicts or bottlenecks
5. Buffer time for unexpected delays (10% contingency)

Format as a Gantt-chart-ready table with: Task Name, Duration, Start Date, End Date, Dependencies, Assigned Role

โš ๏ธ Important: Validate the Timeline

AI-generated timelines are starting points, not final schedules. Always:

  • Review with your team to validate effort estimates
  • Check for resource over-allocation (same person on multiple tasks)
  • Verify dependencies based on your organization's workflow
  • Add buffer time for unknowns (typically 10-20%)
  • Consider team availability (PTO, other projects)

๐Ÿ‘ฅ Resource Allocation Planning

You know what needs to be done and when. Now you need to figure out who does whatโ€”and whether you have enough people.

Creating a Resource Allocation Plan

Create a resource allocation plan for the e-commerce redesign project.

TEAM COMPOSITION:
- 2 UX/UI Designers (Sarah - Senior, Mike - Mid-level)
- 3 Frontend Developers (React specialists)
- 2 Backend Developers (Node.js/Express)
- 1 QA Engineer
- 1 Content Writer
- 1 Project Manager (me)

REQUIREMENTS:
1. Assign roles to each task in the WBS
2. Calculate total hours per person per week
3. Identify resource bottlenecks (anyone over 40 hours/week)
4. Suggest where we might need contractors or additional help
5. Highlight skill gaps (tasks we don't have expertise for)
6. Recommend task sequencing to balance workload

Present as a week-by-week resource allocation table showing:
- Person name and role
- Tasks assigned that week
- Total hours allocated
- % capacity utilization
- Any conflicts or overallocations

Interpreting Resource Analysis

ChatGPT will identify resource issues like:

๐Ÿšจ Overallocation: Sarah (Senior Designer) is assigned 65 hours in Week 3. Need to redistribute work or extend timeline.

โš ๏ธ Skill Gap: Payment gateway integration requires Stripe API expertise. None of your developers have this experienceโ€”consider bringing in a contractor.

๐Ÿ’ก Opportunity: Mike (Mid-level Designer) is only 50% utilized in Weeks 5-6. He could help with design documentation or start on marketing materials early.

โœ… Action Items from Resource Analysis

Use ChatGPT's insights to:

  1. Hire or contract for identified skill gaps
  2. Resequence tasks to avoid overallocation
  3. Negotiate timeline extensions if resources are insufficient
  4. Cross-train team members for underutilized skills
  5. Adjust scope if resource constraints are severe

๐ŸŽ“ Advanced Planning Techniques

Once you've mastered basic WBS and timeline creation, try these advanced prompts:

๐ŸŽฏ Critical Path Analysis

Identify which tasks directly impact your deadline

"Analyze the critical path for this project timeline. Which tasks have zero float (cannot be delayed)? If I need to finish 2 weeks earlier, which tasks should I focus on accelerating?"

โš ๏ธ Risk-Based Planning

Build contingency plans for high-risk tasks

"For each phase in the WBS, identify the top 3 risks that could delay the project. Suggest mitigation strategies and calculate contingency buffer time I should add."

โšก Fast-Track Planning

Find opportunities to run tasks in parallel

"Analyze this timeline for fast-tracking opportunities. Which sequential tasks could potentially overlap? What are the risks of doing so?"

๐Ÿ”ฎ Scenario Planning

Plan for best-case, worst-case, and most-likely scenarios

"Create 3 timeline scenarios: Optimistic (everything goes perfectly), Pessimistic (major delays in design and development), Most Likely (10% buffer on all tasks)."

๐Ÿ’ช Practice Exercise

๐ŸŽฏ Your Challenge: Plan a Mobile App Launch

Scenario: You're launching a new mobile fitness tracking app for iOS and Android.

Requirements:

  • 3-month timeline from today
  • Team: 2 mobile developers (iOS & Android), 1 backend developer, 1 designer, 1 QA tester
  • Features: User registration, workout logging, progress tracking, social sharing
  • Must integrate with Apple Health and Google Fit APIs

Task: Create a complete WBS, timeline with dependencies, and resource allocation plan using ChatGPT.

Sample Starting Prompt

I need to plan a mobile fitness tracking app launch project. Help me create:
1. Comprehensive Work Breakdown Structure (WBS)
2. Project timeline with task dependencies
3. Resource allocation plan

PROJECT DETAILS:
- Timeline: 3 months from today (launch date: [INSERT DATE])
- Platform: iOS and Android native apps
- Team: 1 iOS developer, 1 Android developer, 1 backend developer (Node.js), 1 UX/UI designer, 1 QA tester
- Core Features:
  * User registration/login (email + social auth)
  * Workout logging (custom workouts, sets, reps, weight)
  * Progress tracking (charts, stats, personal records)
  * Social features (share workouts, follow friends)
  * Integration with Apple Health and Google Fit
- Backend: REST API + PostgreSQL database

SPECIFIC REQUIREMENTS:
- Break into phases: Planning, Design, Development (Backend + Mobile), Testing, Launch
- Consider parallel iOS/Android development where possible
- Identify dependencies (backend APIs must be ready before mobile features)
- Flag any resource bottlenecks or skill gaps
- Include app store submission process (1 week review time)
- Add 15% buffer for unexpected delays

OUTPUT FORMAT:
- WBS with 3 levels of detail
- Timeline as Gantt-ready table (Task, Duration, Start, End, Dependencies)
- Resource allocation showing hours/week per person
- Critical path analysis
- Risk areas to watch

โœ… Try It Now!

Open ChatGPT and use this prompt. Spend 20 minutes refining the plan. Compare it to how long it would take you to create this from scratch. That's the power of AI-assisted planning!

๐ŸŽฏ Key Takeaways

  • โœ…
    AI can create a comprehensive WBS in 15 minutes

    What used to take 4+ hours of manual work

  • โœ…
    Provide rich context for better results

    Project type, team composition, timeline, constraints, and deliverables

  • โœ…
    Use iterative refinement

    Start high-level, then drill down into specific phases that need more detail

  • โœ…
    Always validate AI-generated plans with your team

    AI provides excellent starting points, but human expertise validates estimates and dependencies

  • โœ…
    Resource analysis reveals bottlenecks early

    Use AI to identify over-allocation, skill gaps, and opportunities before the project starts

๐Ÿš€ What's Next?

You now know how to create comprehensive project plans in a fraction of the time. In the next module, we'll explore how to use AI for Agile and Scrum workflowsโ€”sprint planning, user stories, retrospectives, and backlog management.

๐Ÿ“š Coming Up in Module 3: Agile & Scrum with ChatGPT

  • Generate user stories with acceptance criteria
  • Facilitate sprint planning in 30 minutes
  • Run more productive retrospectives
  • Create and prioritize product backlogs

๐ŸŽฏ Top Project Management Tools with AI

Streamline planning and tracking with AI-powered PM platforms

๐Ÿ“Š Monday.com AI - Visual Project Management

$10-20/seat/month | AI-powered workflows, automations, and insights

Used by 150,000+ companies. AI generates project plans, predicts delays, automates status updates.

Try Monday.com Free โ†’

๐Ÿ“ Knowledge Check

Test your understanding of AI for project planning!

1. How can AI improve project planning?

A) By making plans unnecessarily complex
B) AI cannot help with planning
C) By generating task breakdowns and timelines efficiently
D) By eliminating the need for planning

2. What role should AI play in creating WBS?

A) AI should never be involved
B) Generate initial structure for PM to refine
C) Replace all PM planning work
D) Make all final decisions

3. What can AI help with in resource planning?

A) Identifying resource needs and potential conflicts
B) Eliminating need for resource allocation
C) Ignoring resource constraints
D) Resource planning is not AI's role

4. How should PMs use AI-generated project plans?

A) Accept without any changes
B) Ignore completely
C) Share directly with stakeholders
D) Review, validate, and customize for context

5. What is a limitation of AI in project planning?

A) AI is perfect at planning
B) AI lacks organizational context and politics understanding
C) AI can read minds
D) AI has unlimited knowledge